Start with the customer’s adoption conditions before filling the schedule

Rather than listing program names in sequence, work back from the product and conditions the customer will accept. First record the delivery model, installation environment, performance to be verified, purchase decision-maker and intended adoption date. Changes to these five items can change the necessary tests and documentation.

TIPA’s Strategic Technology Roadmap for SMEs in Korea provides guidance for technology development and commercialization preparation.[1] A roadmap target does not replace a particular customer’s purchase commitment or your product’s test results. Keep the industry direction and the conditions to verify with this customer in separate fields of the development plan.

NET, NEP and procurement are not a mandatory sequence for every product

Korea’s NET guidance describes eligible technologies including completed technologies with quantitative evaluation indicators established through demonstration testing.[2] The NEP guidance addresses products whose practical development is complete and that apply outstanding core technology, examining performance, quality and a system for ongoing production.[3] Their targets and required documents differ. Do not assume that NET recognition automatically leads to NEP designation.

The Korean Public Procurement Service’s Excellent Product guidance also sets out separate requirements for applied technology, quality evidence, assessment and contracting.[4] Successful development or certification/designation alone does not confirm a purchase contract or revenue. Choose a route that fits the intended sales channel, and check the latest notice, revisions and product-specific conditions when actually applying.

Distinguish product-specific safety, authorization and conformity requirements from certifications or designations intended to recognize technical excellence or support market access. Customer research and production and maintenance preparation can run alongside development. Before starting a field trial or selling, however, check the requirements that apply to that product.

Define the evidence that will authorize the next expenditure

The following is an internal decision table proposed by IRUMJAE, not an official agency assessment form. Add an owner, verification date and document version to each row. Agree in the review meeting on the conditions for proceeding and holding. A scheduled date alone is no reason to pass an unverified item.

Define the evidence that will authorize the next expenditure · Decision table
Review stageEvidence to collectQuestions before proceeding
DevelopmentCustomer requirements, prototype configuration and performance test recordsFor which model and conditions was the target verified? What technical issues remain?
Field validationSite operating conditions, test plan, raw records, and incident and recovery historyWas usability verified within the test scope? What needs checking again if the site changes?
Certification or designationEligibility for the selected scheme, model-specific evidence and a mapping to test recordsDo the application subject and current evidence match? Does a design change require retesting or supplementary documents?
ProcurementIntended purchasing route, specification, technology and quality documents, and supply preparationsDo the documents match the actual delivery model? What follow-up preparation is needed for assessment and contracting?
CommercializationCustomer acceptance conditions, production capacity, supply and maintenance costs, and a payment collection planWho verifies what and decides to purchase? Can the business bear post-delivery responsibilities and recurring costs?

Hypothetical example: identify what to recheck before changing a prototype

This example is fictional and for illustration. A company wants to propose a pump module tested indoors for outdoor equipment. Prototype performance has been verified, but humidity, contamination, extended operation, replacement methods and installation responsibilities remain undecided. Presenting the existing performance test as validation of all outdoor use may create a need to redo documentation later.

First agree with the customer on site conditions and acceptance scope, and check applicable requirements. Define and record the scope that can be tested, then compare the model and configuration with those intended for certification, designation or procurement. If the design or major components change, identify the tests and documents that need rechecking. Do not assume a full retest is always necessary; decide according to the change and the relevant criteria.

Sales materials, production quotations and maintenance plans can be prepared in parallel. Do not record a field-trial discussion or estimated quantities as a confirmed order. At the next meeting, focus on the largest current uncertainty and the expenditure to authorize once it is resolved, rather than simply counting tasks.

Next steps

Contact IRUMJAE with information you can disclose: product and model, target customer and sales channel, current test records, certifications or designations under consideration, and intended adoption date. We can review the dependencies between documents and the sequence of development, field validation and commercialization preparation. Agree on a transfer method before sending confidential material.

Sources & further reading

Sources checked · 2026-11-04

[1] TIPA · Introduction to Korea’s Strategic Technology Roadmap for SMEs: development direction and purpose

[2] Korea Industrial Technology Association · NET eligibility and application guidance (Korea)

[3] Korea Industrial Technology Association · NEP designation overview, eligible products and criteria (Korea)

[4] Korea Public Procurement Service · Excellent Product designation, application, assessment and contracting